Project overview

We Energies and American Transmission Co. are proposing an electric system reinforcement project that involves the construction of a new We Energies substation adjacent to the existing Milwaukee County Substation at 93rd Street and Watertown Plank Road, and construction of two separate 138,000-volt transmission lines to connect the substation to the transmission system that serves area. The project requires approval by the Public Service Commission of Wisconsin. The PSC is expected to complete its review in early 2013.
Need for the project
The Highway 45 corridor in western Milwaukee County is a growing metropolitan business hub. According to We Energies’ planning studies, electric demand in this region is projected to double as soon as 2016, beyond the capacity of the existing distribution substations and feeders that serve the area. Key drivers include commercial growth along Watertown Plank Road and increased electric usage by businesses and homes.
In addition, the critical nature of the two Level 1 trauma centers located within the Milwaukee Regional Medical Complex calls for a higher level of electric service reliability, one that includes a redundant source for electricity in the event that one of the two lines experiences an outage. Two separate and distinct lines are being proposed to serve the new We Energies substation.
The proposed project will:
- Relieve current and projected substation and source line overloads
- Provide needed service level of reliability to MRMC
- Enable planned growth in the area
- Ensure system reliability for homes and businesses
Routing and siting
The Wauwatosa area is a highly developed urban area with dense housing and commercial areas, which has added to the complexity of the routing and siting process. Additionally, the Wisconsin Department of Transportation’s planned Zoo Interchange impacts our project and schedule.
Best routes balance:
- Reliability, operation and maintenance
- Constructability
- Environmental impacts
- Social impacts
- Cost
Public Involvement
A series of public open house meetings during 2011 and periodic mailings provided the public with opportunities to comment on the project and participate in the process. Click here to learn more about ATC’s public involvement process. The PSC will hold public hearings in 2012 where the public can voice their opinions on the project and proposed routes.
PROJECT AT A GLANCE |
| Proposal: |
We Energies Substation and ATC electric transmission lines |
| Area benefited: |
Wauwatosa and western Milwaukee County |
| Length of lines: |
Approximately two miles each |
| Voltage: |
138,000 volts |
| End points: |
Milwaukee County Substation site at 93rd Street and Watertown Plank Road; the proposed transmission project will connect with the existing transmission lines in the area. Those lines are located to the west and south and the endpoints will be determined through the routing and siting and engineering processes.
|
| PSC Docket ID: |
5-CE-139 |
SCHEDULE* |
| Identify potential routes with public involvement: |
|
| Environmental analysis: |
Through Fall 2011 |
| Submit application to Public Service Commission: |
Feb. 2012 |
| Regulatory review and public hearing |
Spring/Summer 2012 |
| Receive PSC decision (anticipated): |
Early 2013 |
| Design line and obtain easements: |
|
| Start construction: |
Summer 2014 |
| Project in-service: |
Spring 2015 |
| *Dates are anticipated and subject to changes |
|